Aspen Wealth · go-live retro.

Day-by-day timeline of how the rollout actually went — milestones, near-misses, what the hyper-care window caught. With the relevant log excerpts inline so the post-mortem doesn't have to be reconstructed later. Use this template for customer retros, deal post-mortems, incident reviews, and launch debriefs.

Aspen Wealth · 8-week onboarding retro

First trade May 6 · zero rollbacks · 1 issue caught in hyper-care
Mar 11 · Week 0 Milestone

Contract countersigned · kickoff scheduled

MSA + SOW closed in 11 days from first call — fastest enterprise close to date. Kickoff call set for Mar 14.

Mar 14 · Week 1 Standard

Kickoff & stakeholder map

All five key stakeholders on the call. Identified Sarah (Head of Ops) as the on-the-ground decision-maker — funnel everything through her.

Mar 18 · Week 1 Standard

Custodian + admin connections initiated

Schwab OAuth completed same day. SS&C connector requested.

[2026-03-18 14:22] custodian.schwab — connection OK (15 accounts)
[2026-03-18 14:24] admin.ssc — request submitted (ticket #88421)
Mar 25 · Week 2 Issue

SS&C file format mismatch — 4 days lost

Admin shipped 2024-vintage schema instead of current. Caught during reconciliation. Recovered with overnight remapping; no critical-path impact, but eats into Week 3 buffer.

[2026-03-25 09:14] admin.parse — err: unknown field "investor_classification"
[2026-03-25 11:02] admin.parse — schema v2024.q3 detected (expected v2026.q1)
[2026-03-26 18:40] admin.parse — remap applied (all 124 records)
Apr 1 · Week 3 Milestone

Stack connected · brand theming locked

Aspen Wealth brand applied across investor portal, advisor app, statements. Aspen logo + Tamarind primary swatch + Hawkes secondary.

Apr 8 · Week 4 Standard

Custom workflow: PE secondaries

Aspen runs a secondary-PE allocation desk; we built three workflows for them. ~3 days of Solutions Eng work.

Apr 15 · Week 5 Standard

Advisor training · two cohorts

14 advisors trained. 100% quiz pass rate. Recordings saved to the Aspen wiki.

Apr 22 · Week 6 Sign-off

UAT signed off · zero open issues

Sarah signed off Friday afternoon. Punch list cleared earlier in the week. Best UAT completion to date.

May 4 · Week 7 Hyper-care catch

Pre-trade rec caught a fund-class mismatch

During mock-trade, the rec found one fund flagged as Class A in our system but Class I at the admin. Fixed in 90 minutes — would have caused a $42K fee error if it had gone live. This is what hyper-care is for.

[2026-05-04 11:15] recon.fund_class — mismatch: Class A vs Class I (fund_id 88421)
[2026-05-04 11:42] ops.aspen — flagged for review (Sarah notified)
[2026-05-04 12:38] admin.confirm — Class I confirmed; correction applied
[2026-05-04 12:40] recon.fund_class — resolved
May 6 · Week 8 Go-live

First trade · $2.4M into Apollo Direct Lending

Clean execution. Trade rec'd at admin in 14 min. Aspen leadership joined the live war room for the hour. Hyper-care continues through May 13.

Lessons + next time

  1. Ship admin file-format check on day 1 — could have caught the SS&C mismatch a week earlier.
  2. Mock-trade is non-negotiable. Two go-lives now where it caught a real issue in the final week.
  3. Custom workflow scoping needs more lead time. PE secondaries surprised us in week 4; bake a "custom workflow check" into kickoff.
  4. Aspen's stakeholder map worked. Funneling through Sarah cut decision time roughly in half versus our last large customer.

Fork & ship

Static HTML. Each event is a <div class="tl-event"> with optional warn / success / milestone modifiers and an optional <pre class="tl-log"> for inline logs.

When to use this

Customer retros, post-mortems, deal-cycle reviews, launch debriefs, advisor onboarding journeys, fund-launch lifecycle reviews.

Reuse ideas

Deal timeline (prospect → close), advisor onboarding journey, fund launch lifecycle, drop-development retro, marketing campaign retro.